Work done after the flood!


In the past 11 weeks, the rifle house, as well as the shooting range and all associated rooms, were cleared of rubble and mud. Furthermore, in this context, the first work for the reconstruction was prepared.


Now the board of directors will submit the necessary documents for the approval of the funding from the state of North Rhine-Westphalia.

The reconstruction and continuation of our brotherhood is in the interests of the Meckenheim citizens, associations and politics. We would like to thank our city and especially our mayor.

Mr Jung, was always at our side with questions and concerns, and he had already provided the signature required to approve the funding.


Now we have to wait before we can continue! We, the board of directors, would like to thank all of the helpers for the work that has been carried out so far to rebuild our property. Furthermore, we would like to thank you in advance for the money donations received, without which the brotherhood would have faced a great challenge.

We would also like to thank you for the donations in kind received.


Here are a few more dates:

Hours worked: Approx. 600 working hours

2 tons of scrap metal

6 m³ Rigipsplatten

6 m³ of wood

18 m³ parquet floor

disposed of in containers.


Work carried out:

- Clear out the workshop and dismantle the cabinets in the workshop.

- Tidying up the kitchen (Schützenhalle) and dismantling the last tall cupboards.

- Setting up tables in the KK stand for storing dishes and materials.

- Dismantling of the counter in the rifle hall.

- Dismantling of the wooden cladding in:

Shooting range LG, entrance hall, as well as the wooden wall at the head of the shooting hall.

- Dismantling the counter second part

- Dismantling of the last wooden cupboards in the entire property

- Dismantling of the lighting system under the ceiling LG booth

- Tidying up the kitchen (Schützenhalle) and dismantling the last tall cupboards.

- Setting up tables in the KK stand for storing dishes and materials.

- Filling the 5 m³ container with wood waste

- Sorting the garbage in the rifle hall

- Dismantling of the electrical system in the air rifle stand

- Dismantling of the side walls of the air rifle system

- Filling the 5 m³ container with wood waste

- Sorting the garbage in the rifle hall

- Dismantling of the electrical system in the air rifle stand

- Dismantling of the side walls of the air rifle system

- Filling the 5 m³ container with rubble

- Dismantling of the central heating (completion)

- Dismantling the ceiling of the air rifle room

- Filling the 5 m³ container with rubble

- Dismantling the gas boiler in the boiler room

- Dismantling of the control cables and electrical cables KK stand / 25 meter room

- Dismantling the tiles in the air rifle kitchen

- Chop off the plaster in the air rifle vestibule

- Cleaning of the floor areas in the 25 meter room and weapons room

- Filling the 5 m³ container with scrap

- Disassembly of the gun cabinets

- Cleaning of the floor areas in the 25 meters, weapons room, LG room and KK anteroom

- Set up toilet facility, construction toilet and dismantle men's toilet.

- Cleaning the hallway shooting range

- Clean 25 meters

- Clean the weapon room

- Remove wallpaper in the LG anteroom and LG kitchen

- Set up toilet facility, construction toilet and dismantle men's toilet.

- Cleaning the hallway shooting range

- Clean 25 meters

- Clean the weapon room

- Remove wallpaper in the LG anteroom and LG kitchen

- Removal of the tiles in the area of the hall (counter)

- Slots trunks for the new supply lines in the counter area

- Removing the tiles in the large hall kitchen

- Cleaning of the two areas (remove building rubble)

- Removing the wallpaper in the LG kitchen area

- Removal of the wallpaper in the entrance area of the LG stand

- Cleaning of the floors in the KK and LG booth

- The windows in the LG booth have been cleaned and maintained

Here in the gallery, all pictures from the last 11 weeks summarized: